Alden Elementary School Claim
Project Name: | Alden Elementary School |
Location: | Duxbury, MA |
General Contractor: | Peabody Construction Co., Inc. (PCC) |
Project Value: | $22,279,219 |
Project Owner: | Town of Duxbury Public School District |
Architect: | DRA, Inc. |
JGCMI Claim Involvement:
- Dispute resolution through negotiated settlements of five Subcontractor surety payment bond claims totaling $656,000
- Analyze the dispute by separating it into – issue by issue, fact by fact, and event by event in order to assess the responsibility, causation and damage components of the dispute
- Complete account reconciliation, prepare settlement options and participate in settlement discussions
- Prepared for and participated in a dispute resolution mediation for a $2.1 million Subcontractor dispute that settled for $1 million
- Collaborate with legal counsel on developing mediation strategy, assist in the decision making process, and help determine the best plan for mediating the dispute
- Gather and help reproduce all of the pertinent documents and organize it into a meaningful data base of core information
- Assist in the preparation of joint pre-trial memorandum, mediation statement and answering interrogatories
- Present CPM delay analysis confirming subcontractor performance delay
- Complete account reconciliation, prepare settlement options and participate in mediation presentation/discussions