Project Name: | Waltham Public Library |
Location: | Waltham, MA |
General Contractor: | Peabody Construction Co., Inc. |
Project Value: | $5,563,781 |
Project Owner: | City of Waltham |
Sector: | Library |
Timeframe: | 1991 – 1994 |
Project Features:
- 20,000 SF renovation
- 28,000 SF addition
- Occupied site
- Masonry restoration
- Refurbish cast iron picket fence
- Stained glass skylight restoration
- Refurbish windows & wood trim
Project Description:
The Waltham Public Library included the restoration of a 20,000 square foot, two – story historically registered building and the addition of a 28,000 square foot, three – story structural steel addition. The work was completed in a dense neighborhood on a tight occupied site. Interior features included: new MEP systems, restoration of windows, wood trim, and a stained glass skylight. Exterior site improvements included masonry restoration, a new parking lot, brick walls and patios, refurbished site fence and extensive landscaping.
Jack Grant Responsibility/Specific Participation:
- Project Executive duties at PCC during construction
- Provided overall leadership and direction to the project management team assisting with subcontractor scheduling, project budgeting and billing, and directly responsible for the owner punch-list/closeout process
Architect:
Shepley, Bulfinch, Richardson, & Abbott
Boston, MA 02210
Structural Engineer:
Robert P. Vallee
Medfield, MA 02052
MEP Engineer:
TMP Consulting
Boston, MA 02110